Create a free Manufacturing.net account to continue

Retrofit Seals Protect Plant Equipment and Personnel

Coal ash can cause a multitude of problems in plants, from increased maintenance costs, safety hazards, to risk for costly equipment failure. See how one western plant dealt with their coal ash problem.

Coal-fired power plants rely on ash conveyor systems to haul ash from their boilers for disposal and allow for continuous coal burning and steam production. At a plant in the western United States, ash slurry leaking from the conveyor was compounding maintenance costs, creating a safety hazard and putting the plant at risk for costly equipment failure.

THE HIGH COST OF A HIGH-MAINTENANCE SEAL

To cool ash before disposal, the ash is sprayed with water as it comes out of the boiler. The combination of ash and water creates ash slurry. While the ash conveyor system is enclosed to contain the slurry, there are potential leakage points at the two shafts that drive the conveyor belt. To seal those shafts, the power plant was using packing.

Under standard operation, packing is a maintenance-heavy sealing method. Packing material is wrapped around the shaft and compressed by a gland to act as a seal and keep product from passing through. Contact and movement from the product and the shaft, however, gradually wears the packing down, and the gland needs to be continually tightened to provide an effective seal. Over time, tightening of the gland becomes ineffective and the seal fails. Due to the abrasiveness of the ash slurry, the packing on the power plant’s ash conveyor wore at a quicker rate than normal, requiring constant maintenance and failing at more frequent intervals.

The failure of the packing allowed the abrasive ash slurry to leak out of the conveyor’s enclosed compartment and into the four adjacent pillow block bearings (two on each shaft), causing those bearings to fail at approximately six-month intervals. With the packing and pillow block bearings each being replaced every six months, the replacement costs, including labor, added up to approximately $5,000 a year. If a bearing failure ever resulted in damage to the shaft and the shaft assembly had to be changed, the costs had the potential to rise into the tens of thousands of dollars.

In addition, the heavy leakage that occurred between packing replacements put the plant at risk for lost time injury, as the leaking ash slurry puddled on the floor. The safety hazard covered a large, high-traffic area, and the chances for a slip/fall incident were unacceptable.

By carefully managing bearing and packing replacements within its regular maintenance schedule, the plant could prevent production losses. The replacement costs and safety hazard, however, made finding an effective sealing solution a high priority.

INPRO/SEAL AIR MIZER PROVIDES PERMANENT SOLUTION

The power plant addressed the leakage by replacing the packing glands with Inpro/Seal Smooth Bore Air Mizer seals. Two replacements were made in May 2011 and after a year of problem-free operation, two more followed in May 2012.

For the power plant’s ash conveyor, Inpro/Seal custom engineered the Air Mizer seals to fi t the 4.4375” (113.7 mm) shafts and the existing bolt hole pattern of the packing gland. Manufacturing was timed so the Air Mizer seals were ready for installation during scheduled downtime. The installation itself was simple: the packing glands were removed, the Air Mizer seals were slid on, the bolts tightened, the air lines connected, and the seal was ready. The retrofit required no modifications to the conveyor system.

A RETURN ON INVESTMENT

Since installation, the Air Mizer seals have eliminated ash slurry leakage, with zero required maintenance. By providing a permanent sealing solution, the plant has saved on maintenance costs, eliminated bearing replacements, increased safety and prevented potential high cost incidents. Plant personnel now have peace of mind about the performance of the seals, bearings and ash conveyor.

ABOUT THE AUTHOR 

Jim Hemingway has been a District Manager for Inpro/Seal for the past 3 years and has over 29 years of rotating equipment experience. 

More